Construction Bulletin

City Projects - Capital Projects Engineering

Courthouse Square Bollards
This project will replace existing non-rated bollards with traffic rated bollards at the intersection of 4th Street and Mendocino Ave and 3rd Street and Santa Rosa Ave to protect users of Courthouse Square from vehicles entering the Square from the north and south approaches. Project will also replace two curb ramps on the north side of 4th Street at Mendocino Ave and one ramp on the west side of the Square, in front of La Rosa Restaurant. Project Details
(M3 Integrated Services, Inc. - Matt McKamey / City - Grant Bailey)

Emergency Well Pump Station – A Place to Play 
The purpose of this project is to convert the existing test well to an Emergency Groundwater Well, along with design and construction of a well pump station and appurtenances associated with the Emergency Groundwater Well at A Place to Play Park. This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water’s Groundwater website located at: https://srcity.org/857/Groundwater. Project Details
(Team Ghilotti - Karen Toso / City - Mimi Arvin)

Fire-Damaged Tree Removal- Parks, Open Space, ROW 
This project is a second phase of fire damaged hazardous tree project and will remove approximately 150 trees within city owned parcels. Concurrently, an arborist will be inspecting additional trees in the burn area that have not been evaluated to identify trees for a third removal contract. Project Details 
(Arborist Now, Inc – Josh Johns / City Greg Loraditch)

Fire-Related Repairs of Utility Stations
This project will undertake rehabilitation efforts at the several potable water stations, reservoirs and sewer lift stations that sustained damage during the Tubbs Fire. Project Details
(Pacific Infrastructure Corporation - Mark Jorgenson / City PM - Eric Frye)

Guerneville Road Pedestrian Path
This project will provide sidewalk on the north side of Guerneville Road between Ridley Avenue and Marlow Road to improve pedestrian accessibility to the area. Though temporary impacts to your neighborhood are inevitable, our goal is to improve our community infrastructure without creating any more disturbance than necessary. The work will occur between 8am and 5pm Monday through Friday. The construction activities are only expected to impact the west bound traffic on Guerneville Rd in the area. Project Details
(City of Santa Rosa Facilities Maintenance Team – Josh Carstensen)

Installation of Public Restroom in Downtown Area
Installation of The Portland Loo, a 24-hour prefabricated single-occupant public restroom. The restroom will be installed in front of City Hall Annex at 90 Santa Rosa Avenue. Site work for the restroom foundation and accessibility is completed. The restroom will be delivered the week of August 24, and will require single lane traffic closure and pedestrian detours expected to last approximately one day. The final phase is to connect the building to utilities and is expected to be completed by the end of September, however, public opening is contingent on public health safety during the coronavirus pandemic. Project Details

La Paloma Ave, East Haven Dr, Rogers Way Sewer and Water System Improvements
This project is one phase of the replacement of Grace Tract neighborhood water and sewer mains. Sewer and water main replacements planned for this phase of work include:

  • East Haven Dr from 4th St to Eleanor,
  • La Paloma Ave from East Haven Dr to Rogers Way, and
  • Rogers Way from La Paloma Ave to 4th St.

Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing sewer main pipe reduces inflow and infiltration and also reduces maintenance costs. All streets will be reconstructed and minor storm drain and pedestrian ramp improvements will be made throughout the project area. Project Details
(Argonaut Constructors - Trevor Stewart / Green Valley Consultants - Sean Lawson / City - Grant Bailey)

Llano Trunk-West Third St Brittain to Darla and Glenbrook Siphon Lining 
This project will rehabilitate approximately 3,800 feet of deteriorating reinforced concrete pipeline (RCP) with cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe, located on W. 3rd Street from Brittian Lane to Darla Drive. Seven manholes along the pipeline will be rehabilitated with a corrosion resistant epoxy liner for protection against future hydrogen sulfide deterioration. The project will also rehabilitate the Glenbrook Sewer Siphon with cured-in-place pipe (CIPP) lining inserted into the three largest barrels. The forth and smallest existing barrel will be abandoned. The two siphon structures will be rehabilitated with a polyurethane liner. Project Details
(SAK Construction - Todd Chalk / PSOMAS - Steve Brandt, Inspector / PSOMAS - Justin Seufert, CM / City - David Fradelizio, PM)

Mayacamas Pump Station Roof Replacement
This project will replace the roof at the Mayacamas Pump Station on the Geysers Pipeline. The roof has begun leaking and was damaged in the Kincade fire. This will provide a long-term solution for a critical facility, while protecting the surrounding natural landscape. Project Details
(Best Contracting Services, Inc. - Wes Fleming / Green Valley Consultants - Rich Gordon / City - Adam Rausch, PM)

Montgomery Dr Water System Improvements - Mission Blvd to Jackson Dr
This project will replace a parallel 4" steel water (1947) main and a 6" ACP water main (1969) with a single 8" water main from Montgomery Drive and from Mission Boulevard to Jackson Drive. The 4" steel main is of primary concern and a new single main will reduce maintenance costs. Project Details
(Argonaut Constructors - Trevor Stewart / City - Chris Huffman)

North Trunk Sewer Replacement - Mendocino Ave to Terra Linda Dr
Project will address the existing lack of accessibility to the north trunk sewer main for routine maintenance and risks associated with traversing adjacent to and/or under an existing watercourse. Work in Chanate Rd may be shut down in the event of a PSPS situation to facilitate traffic flow. Project will also relocate 1,950 feet of existing 12-inch and 15-inch vitrified clay pipe (VCP) sewer main located adjacent to Paulin Creek and 1,350 feet of existing 15-inch reinforced concrete pipe (RCP) located in Mendocino Ave and Lomitas Ln. 1,866 feet of 8-inch water main will be installed in various parts of Chanate Rd, Lomitas Ave and Lomitas Ln to both increase and upgrade the existing water system and provide separation from the new sewer main. Info: http://www.chanatesewerproject.com. Project Details
(Team Ghilotti - Sean Durenberger / Green Valley Consultants - Sean Lawson / City - Cy Penry)

Northerly Slope Protection Delta Pond
Wave action from wind and storm events have caused significant erosion benches on the northerly slope of reclaimed water Delta pond. The project consists of rehabilitating approximately 5,200 linear feet of Delta Pond northerly embankment and installation of a coffer dam. Rehabilitation method consists of excavating and compacting approximately 2.5 ft. of the slope embankment and placing approximately 1 ft. of rock rip rap over geotextile to protect the embankment from wave erosion and vegetation. Project Details
(Granite Construction / B&R - Dana Brock / City - Michael Mirich)

Pacific Ave Reconstruction - Humboldt St to Montecito Ave
This project will repave Pacific Avenue between Humboldt Street and Montecito Avenue. The project will also include curb ramps, replacement of a short section of sewer main on Pacific Avenue and a sewer main supporting 1320 North Street as well as a large section of the water main, replacement of water services and hydrants, drainage improvements, Rectangular Rapid Flashing Beacon (RRFB) systems at King Street, Beaver Street and Elizabeth Way/Spring Street intersection. -Video Detection System at Humboldt Street, North Street and McDonald Avenue. Though temporary impacts to your neighborhood are inevitable, our goal is to improve our community infrastructure without creating any more disturbance than necessary. The work will occur between 8am and 5pm Monday through Friday. The construction activities are expected to be phased to allow traffic through the area. Street parking is expected to be affected. Traffic Delays should be expected, but services to the residents (mail, garbage, transit stops etc.) will be coordinated with by the construction. Project Details 
(Argonaut Constructors – Dan Giordani / Green Valley Consultants – Mel Manni / City – Mimi Arvin)

Pump Station 15 Upgrades
This project will perform upgrades to the City water pumping facility in the Oakmont neighborhood installing a higher energy efficient motor starter on the largest pump (VFD), replaces the emergency standby power generator, re-coat the hydro-pneumatic tank, and replace outdated controls and instrumentation equipment to reduce maintenance and improve system reliability. Project Details
(Bartley Pump PM, LLC -Jason Smith / Coastland Engineers - Bob Elze / City - Eric Frye)

R7 Road Access and Stabilization Repairs 
This project is designed to improve drainage, rehabilitate an existing access road, and implement slope stability repairs along the access road to City Reservoir 7 (R7) which is a vital piece of the City’s potable water infrastructure. Upgrades to the existing storm drain systems on portions of Yerba Buena Road will be included in this project. Project Details 
(Ghilotti Construction - Chase McPhaul / Coastland Engineers - Mike Janet / City - Erich Rauber)

SMART Hearn Avenue Multi-Use Path Crossing
The City of Santa Rosa is contracting with St. Francis Electric for the installation of a signalized crosswalk at the Sonoma-Marin Area Rail Transit (SMART) railroad tracks located at Hearn Avenue. The crosswalk will be installed on the east side of the railroad tracks, which will require a portion of the existing median island to be removed to accommodate the crosswalk. The crosswalk will be connected to the railroad equipment to turn red in conjunction with the railroad crossing activation. January 2021 to April 2021. Project Details
(St. Frances Electric - Mike Hendrickson/ City - Chad Anderson)

Skyfarm A and Hansford Ct Sewer Lift Station Reconstruction
This project will reconstruct two lift stations that were severely damage during the Tubbs Fire.
One station is located on SkyFarm Drive near Saint Andrews Drive and the other station is at the end of Hansford Court. Project Details
(Pacific Infrastructure Corporation – Jon Re/ Coastland Engineers – Mike Janet/City – Eric Frye)

Private Development Projects – Engineering Development Services

575 Ross St.
EP20-0235
Sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through March 2021.
(Kaelan Construction – Colin Scott 808-896-5818 / City – Javier Fernandez, Charles Robinson)

Airway Community Care – 3731 Airway Drive
City File #2018-0008 – EP19-0687
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2021
(Serres Construction - John Serres 707-799-5557/City – Javier Fernandez)

Art House – 620 7th Street
City File #2019-0004 – EP19-0150
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2021.
(Brian Wheeler 707-217-3999 /City – Javier Fernandez, Lionel Rocha)

Baggett Cottages – 1084 Dutton Ave (X Barham)
City File #2020-0016 - EP
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through March 2021
(Rod Baggett – 707-495-3477 /City – Javier Fernandez, Lionel Rocha)

Doubles Dr. (1001)
City File #2019-0052 - 
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through March 2021.
(Northwest General Engineering - James Golsby 707-326-5282 / City - Javier Fernandez, Charles Robinson)

Dutton Avenue Subdivision (895)
City File #2010-0004 – EP19-1327
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through April 2021.
(Mike Harris Construction - Mike Harris 707-478-5374 /City – Javier Fernandez, Charles Robinson)

Dutton Flats Apts. – 214 West Third St.
City File #2020-0010 (EP20-0677)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through April 2021.
(Northwest General Engineering - Ben Guillory – 707-888-9120 /City - Javier Fernandez, Charles Robinson)

Fulton Road Widening Project – Guerneville Road to Piner Road Rule 20A, Utility Undergrounding & Electrical Panel Conversions
EP20-0648
Utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through August 2021.
(West Valley Construction – Daniel Lynam 650-280-3140/ City – Chad Anderson)

Gardens Subdivision – 713 West Third
City File #2018-0014 – EP18-0257
Street, sidewalk and utility improvements.
(Ryan Novak – 707-623-5880 /City – Javier Fernandez, Lionel Rocha)

Kawana Meadows Subdivision – Franz Kafka Ave at Kawana Terrace
 File #2005-0040 – EP15-0548

Street, sidewalk and utility improvements.
(Scott Waterworth 510-590-8094 /City - Javier Fernandez, Lionel Rocha)

Kawana Springs Apartments - Kawana Springs Road at Petaluma Hill Road
City File #2018-0030 – EP19-0555
Street, sidewalk and utility improvements.
(Precision Construction – Don Wampler 415-942-3875 /City - Javier Fernandez, Lionel Rocha)

Lantana Homes – 2979 Dutton Meadows
City File #2019-0039 – EP19-1168
Street, sidewalk and utility improvements.
(Midstate Construction – Guy Raggio – 707-975-7622 /City - Javier Fernandez, Lionel Rocha) 

Liner Village Subdivision – 2063 Dennis Ln / 3804 Elwin Ln
City File #2018-0024 – ENGG20-004
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2021.
Street, sidewalk and utility improvements.
(Jason Jones Construction – Jason Jones – 707-543-6529 /City - Javier Fernandez, Charles Robinson)

Lodge at Piner Rd – 1980 Piner Rd
City File #2020-0014 - EP20-1184
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2021.
(Northwest General Engineering - Ben Guillory – 707-888-9120 /City - Javier Fernandez)

Marlow Commons Subdivision – 2039 Guerneville Rd.
City File #2019-0037 – EP19-1291
Street, sidewalk and utility improvements.
(Argonaut Constructors – Dan Giordani – 707-280-4986 /City - Javier Fernandez)

Miller Village & Auberge Du Soleil II - 2121/2113 Dennis Lane
City File #2017-0035 - EP17-0596

Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2021.
Street, sidewalk and utility improvements.
(Jason Jones Construction - Jason Jones (707) 543-6529 / City - Javier Fernandez)

Recess Storage – 4224 Hwy 12 
City File #2021-0001 – EP21-0074
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2021.
Street, sidewalk and utility improvements.
(RCX Inc – Dale Smith – 707-328-8286 /City - Javier Fernandez, Charles Robinson)

Round Barn Village – 1 Round Barn Blvd.
City File # 2020-0004 - EP20-0175
On-site grading and private improvements.
(Northwest General Engineering Mike Gully – 707-481-2763 /City – Javier Fernandez)

Sage Commons – 80 College Ave. 
City File #2020-0033 – EP21-0053
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through May 2021.
(Peters Excavating – Ron Peters 707-953-6136 /City - Javier Fernandez)

Santa Rosa Community Based Outpatient Clinic – 2285 Challenger Way
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through April 2021.
(AFelix General Engineering - Adam Felix 707-806-9370 /City - Javier Fernandez, Lionel Rocha) 

Session Climbing & Fitness – 965/983 South A Street 
EP20-0341
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2021.
Street, sidewalk and utility improvements.
(RCX Inc – Dale Smith – 707-328-8286 /City - Javier Fernandez, Charles Robinson)

Southwest Estates – Bellevue Ave/Burgess Dr. 
City File #2017-0039
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through May 2021.
(Northwest General Engineering Adam Holzinger – 707-975-6769 /City - Javier Fernandez, Lionel Rocha)

Stony Village North – 2729 Stony Point Rd 
City File #2020-0001
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through October 2021.
(Northwest General Engineering – Mark Casarotti – 707-974-4568 /City - Javier Fernandez)

 

All dates and times are subject to change.
Work will be done Monday through Friday unless otherwise noted.
Access for emergency vehicles will be provided.
 Postal delivery will continue as usual.