Construction Bulletin

City Projects - Capital Projects Engineering

Accessibility Alterations at Howarth Park
This project will level and replace asphalt with concrete around the carousel, construct an accessible ramp system through the picnic area by the carousel, and improve access to the animal barn and pony rides at Howarth Park. The park will remain open during construction. Construction will be completed in June 2020, the picnic area by the carousel will remain closed through July 2020 to allow the new lawn to establish.
Project Details
(M3 Integrated Services, Inc / City - Randy Lopez)

Bicycle and Pedestrian Gap Closures - Piner Rd and N. Dutton Ave
The first location will rehabilitate the outside lanes of pavement and provide Class II bike lanes completing the existing gap on Piner Road between Coffey Lane and Range Avenue. The second location will provide a sidewalk on the east side of Dutton Avenue just south of Jennings Avenue. The project will also install eleven (11) ADA compliant curb ramp upgrades for improved accessibility. Night work is expected for this project on Piner Road for a limited time for some of the paving operations; work during overnight hours is to reduce the impact to traffic and businesses during paving work. Otherwise, short term lane closures and delays should be expected in the project area. Driveways will remain open or alternative route provided. For more information see the Project Details
(Ghilotti Construction Company - Matt McDonald / Coastland Engineers – Adam Felix / City – Lisa Guderian)

City Hall Campus Sidewalk Reconstruction Phase 1
The project will upgrade sidewalk, driveways and curb ramps at the following locations: City Hall Annex - 90 Santa Rosa Ave (west side only), 635 First Street (east side only), and Parking Garage 9 (D Street side only.) Short term lane closures and delays should be expected in the project area.
City Hall Annex - 90 Santa Rosa Ave public access will be maintained the entire project. Driveway construction will close the drive-thru option at the City Hall Annex building for a limited time; pedestrian access will be provided during working hours and alternative route will be identified.
Vehicular access to the Parking Garage on D St. will be provided at all times. Driveway construction will be phased. Pedestrian access may be routed through Comstock Mall for a portion of the project. For more information please visit the web page: Project Details
(Vanguard Construction, Inc / City - Randy Inselman)

Class II Bike Lane Gap Closures
Project will close gaps in the Class II bicycle lane on Piner Road between Marlow Road and Coffey Lane, W. Third Street between Stony Point Road and Brittain Lane and Hopper Avenue between Coffey Lane and Airway Drive. The project will re-stripe segments and design will ensure that changes made will have minimal reduction to the level of service at the intersections. Project Details
(Bayside Stripe & Seal – Ramy Mughannam / City – Kevin Ryan)

Coffey Neighborhood Park 
This project will rebuild the fire damaged park, remove existing fire blown debris, and replace it with new playground   equipment, meandering sidewalk and pedestrian ramps, a dog park, new picnic tables, benches, and health   stations. The 5 acre site will also have new trees, sod, and irrigation installed along with outdoor lighting. January   2020 to September 2020. Project Details 
(Team Ghilotti - Karen Toso / City - Bernie Alabona)

Emergency Well Pump Station – A Place to Play 
The purpose of this project is to convert the existing test well to an Emergency Groundwater Well, along with design and construction of a well pump station and appurtenances associated with the Emergency Groundwater Well at A Place to Play Park.This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water’s Groundwater website located at: https://srcity.org/857/Groundwater. Project Details 
(Team Ghilotti - Karen Toso / City - Mimi Arvin)

Farmers Lane Well Rehabilitation Project/Farmers Lane Well Facility Pump Replacement Project
The final construction phase of the Farmers Lane Well Rehabilitation Project/Farmers Lane Well Facility Pump Replacement Project has been completed, however various minor tasks remain. Project Details 
(Pacific Infrastructure - Mark Jorgenson / City - Erich Rauber)

Fire Damaged Street Lights Replacement in Coffey Park 
Remove and replace 130 street light standards and new conduit in the Coffey Park Neighborhood. May 2020 to   August 2020. Project Details 
(St. Frances Electric - Sean Oconell / City - Bernie Alabona)

Fire Damaged Street Lights Replacement In Fountaingrove
Remove and replace forty (40) Street Light standards along Fir Ridge Drive and Southridge Drive in Fountaingrove. Project Details
(Joe Lunardi Electric – Ray Lunardi / City – Greg Loraditch)

Fire-Damaged Tree Removal- Parks, Open Space, ROW 
This project is a second phase of fire damaged hazardous tree project and will remove approximately 150 trees   within city owned parcels. Concurrently, an arborist will be inspecting additional trees in the burn area that have not   been evaluated to identify trees for a third removal contract. Project Details 
(Arborist Now, Inc – Rich Mathey / City Greg Loraditch)

Flashing Yellow Arrow Retrofit
Retrofit and upgrade thirty-nine (39) Protected/Permissive signalized intersections with Flashing Yellow Left Turn Arrow displays to meet the current MUTCD/CAMUTCD Standards. Project Details
(DC Electric Group – Tim Carter / City – Dave Stolte)

Llano Trunk-West Third St Brittain to Darla and Glenbrook Siphon Lining 
This project will rehabilitate approximately 3,800 feet of deteriorating reinforced concrete pipeline (RCP) with cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe, located on W. 3rd Street from Brittian Lane to Darla Drive. Seven manholes along the pipeline will be rehabilitated with a corrosion resistant epoxy liner for protection against future hydrogen sulfide deterioration. The project will also rehabilitate the Glenbrook Sewer Siphon with cured-in-place pipe (CIPP) lining inserted into the three largest barrels. The forth and smallest existing barrel will be abandoned. The two siphon structures will be rehabilitated with a polyurethane liner. Project Details
(SAK Construction, Todd Chalk / PSOMAS, Steve Brandt, Inspector / PSOMAS, Justin Seufert, CM / City, David Fradelizio, PM)

Pavement Preventive Maintenance 2020 
This project will consist of performing preventive maintenance on City streets. Work to be completed is crack sealing, localized asphalt repairs, pavement resurfacing, and striping reconfiguration at select locations. Contract work will occur along the following street segments:

  • Brookwood Ave between Sonoma Ave and Maple Ave
  • E St between College Ave and Sonoma Ave
  • South Hendley St between Bennett Valley Rd and Aston Ave
  • Aston Ave between South Hendley St and Brookwood Ave
  • Allan Way between Brookwood Ave and Cooper Dr
  • Petaluma Hill Rd from Colgan Ave to City Limits
  • Kawana Springs Rd between Santa Rosa Ave and City Limits

Striping reconfigurations, including addition of Class II Bicycle lanes, will also occur on the following street segments:

  • E St between College Ave and Sonoma Ave
  • Kawana Springs Rd between Santa Rosa Ave and Petaluma Hill Rd
  • Kawana Springs Rd between Brookwood Ave and City limits. Project Details

(Sierra Nevada Construction - Nick Bacher / Green Valley Consulting Engineers - Sean Lawson / City - Grant Bailey)

Pump Station 15 Upgrades 
This project will perform upgrades to the City water pumping facility in the Oakmont neighborhood installing a higher energy efficient motor starter on the largest pump (VFD), replaces the emergency standby power generator, re-coat   the hydro-pneumatic tank, and replace outdated controls and instrumentation equipment to reduce maintenance and improve system reliability. Project Details 
(Bartley Pump PM, LLC -Jason Smith / Coastland Engineers - Bob Elze / City - Eric Frye)

R7 Road Access and Stabilization Repairs 
This project is designed to improve drainage, rehabilitate an existing access road, and implement slope stability repairs along the access road to City Reservoir 7 (R7) which is a vital piece of the City’s potable water infrastructure. Upgrades to the existing storm drain systems on portions of Yerba Buena Road will be included in this project. Project Details 
(Ghilotti Construction - Chase McPhaul / Coastland Engineers - Mike Janet / City - Cheryl Everson)

R9C Tank Decommission and Demolition 
Reservoir R9C (formerly known as R9A) is located at 4788 Bennett Valley Road. This tank is past its design life, and was replaced by the new R9A & R9B tanks. Tank was disconnected from distribution network at intersection of Bennett Valley Road at Yulupa Road in 2014. Decommissioned tank will be demolished, the pipeline to the tank will also be capped at both ends at the time of tank removal and the site will be restored to pre-development conditions. Project Details 
(Resource Environmental Inc., Richard Miller / City -Oscar Serrano, Inspector –/ City-David Fradelizio, PM/CM)

Station 2 Emergency Generator Replacement and Station 3 Power Filter Installation 
This project will install a filter to eliminate harmonic feedback to ensure proper operation of the emergency generator at the Station 3 pump station. Additionally, this project will replace the existing emergency generator at Station 2. Project Details 
(CES CORP/Cal Electric – Perry Bien / City – Eric Frye)

Stony Point Road Reconstruction and Widening  Phase - 2 - Sebastopol Road to Hearn Avenue
The final construction phase of the Stony Point Road widening and reconstruction project has been completed, however various minor tasks remain. Check back for updates. Project Details
(City - Mimi Arvin, Construction Manager)

Private Development Projects - Engineering Development Services

AC Hotel – 300 Davis Street (4th and 5th Street)
City File #2019-0007 – EP19-0201
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2020.
(Northwest General Engineering/City – Javier Fernandez)

Airway Community Care – 3731 Airway Drive
City File #2018-0008 – EP19-0687
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2020.
(Serres/Harris Construction/City – Javier Fernandez)

Art House – 620 7th Street
City File #2019-0004 – EP19-0150
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2020.
(Sunshine Construction/City – Javier Fernandez, Lionel Rocha)

Commercial Court (Inn at Santa Rosa) – 111 Commercial Court
City File #2018-0033 – EP18-0585
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2020.
(Carlisle Construction/City - Javier Fernandez)

Dutton Avenue Subdivision (895)
City File #2010-0004 – EP19-1327
 
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through November 2020.
(Mike Harris Construction/City – Javier Fernandez, Charles Robinson)

Gardens Subdivision – 713 West Third
City File #2018-0014 – EP18-0257
Street, sidewalk and utility improvements.
(Argonaut Constructors/City – Javier Fernandez, Lionel Rocha)

Kawana Meadows Subdivision - Kawana Springs Road at Petaluma Hill Road
City File #2005-0040 – EP15-0548

Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2020.
(Argonaut Constructors/City - Javier Fernandez, Lionel Rocha)

Kawana Springs Apartments
City File #2018-0030 – EP19-0555

Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2020.
(Northern Pacific Construction/City - Javier Fernandez, Lionel Rocha)

Lantana Homes – 2979 Dutton Meadows
City File #2019-0039 – EP19-1168
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2020.
(Ghilotti Construction/City - Javier Fernandez, Lionel Rocha)

Marlow Commons Subdivision – 2039 Guerneville Rd.
City File #2019-0037 – EP19-

Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2020.
(Argonaut Constructors/City - Javier Fernandez)

PG&E Stony Point Rd Gas transmission main replacement
EP20-0275 *Night work approved*

1,250 of gas transmission main replacement
Traffic control 10 pm. - 6 am., Monday to Friday, through September 2020.
(PG&E – Barnard Pipeline Construction/City – Javier Fernandez, Charles Robinson)

Round Barn Village
Grading Permit #ENGG19-003 - EP20-0175

On-site grading
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday through December 2020.
(Northwest General Engineering/City – Javier Fernandez)

SR Medical Arts Plaza – Montgomery Dr./Sotoyome St./Sonoma Ave.
City File #2019-0036 

Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2020.
(Ghilotti Construction/City - Javier Fernandez, Lionel Rocha)

Southwest Estates – Bellevue Ave/Burgess Dr.
City File #2017-0039

Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2020.
(Northwest General Engineering/City - Javier Fernandez, Lionel Rocha)

Villas Apartment Project Phase 1&2 – 1755 Sebastopol Rd (Hampton Way)
City File #2018-0038, 0039- EP17-0715
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2020.
(Northwest General Engineering/City – Javier Fernandez, Charles Robinson)

 


All dates and times are subject to change.
 Work will be done Monday through Friday unless otherwise noted.
 Access for emergency vehicles will be provided.
 Postal delivery will continue as usual.